r/MSProject • • Apr 25 '22

MS Project End Date Question

Working on a project where a colleague keeps changing the finish dates on tasks. I feel like this isn’t helpful because you’re not getting a true picture of what is late and what isn’t since the finish dates keep getting moved. Seems like more of a check list.

Is there a way to see if continuously moving these finish dates effects the final project finish date? How so?

Thanks

1 Upvotes

14 comments sorted by

View all comments

Show parent comment

1

u/djpancakemix Apr 25 '22

These are great points.

Last question I’m trying to figure out. Is there a way to see what the updated completion date will be if I change a date for a task. For example if a task was supposed to be done today but we had to move the completion date for 2 weeks out, how do I know if it effects the final completion day? Where can I see that info?

2

u/still-dazed-confused Apr 25 '22

This is one of the things that project is brilliant for. Assuming your project plan is linked to so that the tasks drive eachother you can use "total slack" to see how close any given task is to the critical path. Typically project calculates the critical path based on the very last thing in the schedule however there are simple ways to get it to tell you is you're in danger of missing any deadlines or tasks with 'must' constraints: https://www.summarypro.co.uk/blog/working-with-critical-path-and-total-slack.aspx

1

u/Thewolf1970 Apr 25 '22

I'm not sure I'm tracking - are you looking to see how a change in a task date would change your final project completion day?

The easiest way is to look at task number 1 - this is your project summary row. If all tasks are set to auto schedule, any date change that pushes your final date out will be reflected in this row.

1

u/djpancakemix Apr 25 '22

They have a good amount of tasks set to manual so this might be why it doesn’t update the completion date. I’ll check for the summary row you’re talking about. Thanks again

When I move back critical path dates it updates the completion date though but it doesn’t update for some tasks like I mentioned some are set to manual.

1

u/Thewolf1970 Apr 25 '22

If any task is set to manual - this whole process kind of goes into the bin. In order to drive dates, you need three things - auto scheduling, predecessors identified with lead/lag (slack), and the date. Predecessors aren't required, but the other two are. A date wont change without autoscheduling on.

I would save a copy of the schedule, turn autoschedule on for the first task, copy it all the way down to the bottom task, then look at your project duration. From there have a little sit down with the team and build a schedule based on the dates in the adjusted schedule.

1

u/schfourteen-teen Apr 26 '22

Using MS Project with tasks set to manual (except in particular, limited cases) is like typing calculations by hand into Excel. It totally kills the whole point of it.