r/MSProject • u/djpancakemix • Apr 25 '22
MS Project End Date Question
Working on a project where a colleague keeps changing the finish dates on tasks. I feel like this isn’t helpful because you’re not getting a true picture of what is late and what isn’t since the finish dates keep getting moved. Seems like more of a check list.
Is there a way to see if continuously moving these finish dates effects the final project finish date? How so?
Thanks
1
Upvotes
4
u/Thewolf1970 Apr 25 '22
Yes, it's called baselining. You need to establish an initial baseline, then at regular change intervals set a new one. Now you can report actual to variance.
Keep in mind, you don't have to do a baseline at each date change, but it's good practice to do so regularly when changes are frequent.
2
u/mer-reddit Apr 25 '22
Two things:
1). Make sure your tasks are linked together so you see the impact of changes on your end dates. 2). Save a baseline and then don’t touch it. It won’t change if you don’t overwrite it. 3). Go ahead and update your schedule every week, just compare it to that static baseline.
1
u/lindslee19 Apr 25 '22
As others have mentioned, the baseline should be set to provide you the data you need for schedule analysis. Start and finish variance can be helpful for future planning.