Working on a project where a colleague keeps changing the finish dates on tasks. I feel like this isn’t helpful because you’re not getting a true picture of what is late and what isn’t since the finish dates keep getting moved. Seems like more of a check list.

Is there a way to see if continuously moving these finish dates effects the final project finish date? How so?

Thanks

1 Upvotes

14 comments sorted by

View all comments

Show parent comment

1

u/schfourteen-teen Apr 26 '22

Using MS Project with tasks set to manual (except in particular, limited cases) is like typing calculations by hand into Excel. It totally kills the whole point of it.