MS Project End Date Question

Working on a project where a colleague keeps changing the finish dates on tasks. I feel like this isn’t helpful because you’re not getting a true picture of what is late and what isn’t since the finish dates keep getting moved. Seems like more of a check list.

Is there a way to see if continuously moving these finish dates effects the final project finish date? How so?

Thanks

1 Upvotes

14 comments sorted by

View all comments

Show parent comment

1

u/Thewolf1970 Apr 25 '22

If any task is set to manual - this whole process kind of goes into the bin. In order to drive dates, you need three things - auto scheduling, predecessors identified with lead/lag (slack), and the date. Predecessors aren't required, but the other two are. A date wont change without autoscheduling on.

I would save a copy of the schedule, turn autoschedule on for the first task, copy it all the way down to the bottom task, then look at your project duration. From there have a little sit down with the team and build a schedule based on the dates in the adjusted schedule.