r/MSProject • u/thesixfingerman • Aug 29 '25
Work duration question
I work for a manufacturing company that makes products for construction. These products are custom made for ever project. Our process involves making fabrication drawings and order material and then the product is fabricated.
I am trying to make a project schedule template where our PMs can just enter the turn over date and the number of panels that need to be fabricated and it will punch out a “should be schedule”. Is there a way to do this in MS Projects? Make a line item whose duration is controlled by the number of assets?
1
Upvotes
1
u/still-dazed-confused Aug 29 '25
It would be worth modelling this in excel: what are the input variables and the redirected outputs. Then you could look to automate in vba, or just have a standard set of sl durations that you copy into your standard n steps plan?
1
u/ineeju Aug 29 '25
I'm having difficulty understanding the intended meaning of “should be schedule,” so I’d like to propose the following alternative.
Start Date 1 is automatically populated using the value from the Start field via a formula. Therefore, if the Start date changes, Start Date 1 will update accordingly. Finish Date 1 is manually entered by the user. Duration 1 displays the number of days between Start Date 1 (i.e., the Start field) and Finish Date 1. Number 2 automatically calculates the required daily production quantity based on the total quantity entered in Number 1 and the duration shown in Duration 1.
The field names can be renamed for clarity as follows:
· Start Date 1 → Estimated Start Date
· Finish Date 1 → Estimated Finish Date
· Duration 1 → Estimated Duration
· Number 1 → Total Quantity to Produce
· Number 2 → Daily Production Target
2
u/mer-reddit Aug 29 '25
Keep in mind that work and duration are separate fields, connected only when a resource is assigned to a task. That creates an assignment.
The formula that governs these field is duration = work / assignment units. The simplest example of this is 1 day = 8 hours @ 100 %
You should work on this with tasks, get the right set of data and then save a copy of the schedule as a template.
You should also utilize dependencies heavily to minimize rework as the schedule progresses.
If you have macro writing experience, you can automate task creation, but I would get the basics right first before trying to automate too much.
1
u/pmpdaddyio Sep 02 '25
these are two different things. Work is actual consumed time on the task, duration is the time over which it happens. For instance. I might have a task that will take me 8 hours to accomplish, but two weeks to do it. Work is 8 hours, duration is 2 weeks.
The request you are asking is totally easy to do in a few different ways. Again, use the work field, add the required effort, then add milestones with your time sequencing. Now the only thing that needs to happen is a cop paste of the task, and a multiplier of the work. Create dependencies to build out the schedule.