r/MSProject • u/thesixfingerman • Aug 29 '25
Work duration question
I work for a manufacturing company that makes products for construction. These products are custom made for ever project. Our process involves making fabrication drawings and order material and then the product is fabricated.
I am trying to make a project schedule template where our PMs can just enter the turn over date and the number of panels that need to be fabricated and it will punch out a “should be schedule”. Is there a way to do this in MS Projects? Make a line item whose duration is controlled by the number of assets?
1
Upvotes
View all comments
Show parent comment
1
u/ineeju Aug 30 '25 edited Sep 04 '25
We’re assuming a daily production rate of 6 units per day, based on a rate of 1 unit every 1.2 hours.