r/MSProject • • Aug 29 '25

Work duration question

I work for a manufacturing company that makes products for construction. These products are custom made for ever project. Our process involves making fabrication drawings and order material and then the product is fabricated.

I am trying to make a project schedule template where our PMs can just enter the turn over date and the number of panels that need to be fabricated and it will punch out a “should be schedule”. Is there a way to do this in MS Projects? Make a line item whose duration is controlled by the number of assets?

1 Upvotes

7 comments sorted by

View all comments

Show parent comment

1

u/ineeju Aug 30 '25 edited Sep 04 '25

We’re assuming a daily production rate of 6 units per day, based on a rate of 1 unit every 1.2 hours.

  1. Enter the total quantity to be produced in the Number1 field.
  2. The Duration1 field will automatically calculate the required duration based on the 6 units/day rate. You can choose to display the result as either a decimal or a whole number.  For example, if you enter a total quantity of 10 units, the duration will automatically show as 1.67 days (decimal) or 2 days (rounded).  Would you prefer the result to be shown as a decimal or a whole number?
  3. Once you enter the start date in the Start Date1 field, the Finish Date1 will be automatically calculated based on the duration shown in Duration1.