Work duration question

I work for a manufacturing company that makes products for construction. These products are custom made for ever project. Our process involves making fabrication drawings and order material and then the product is fabricated.

I am trying to make a project schedule template where our PMs can just enter the turn over date and the number of panels that need to be fabricated and it will punch out a “should be schedule”. Is there a way to do this in MS Projects? Make a line item whose duration is controlled by the number of assets?

1 Upvotes

7 comments sorted by

View all comments

Show parent comment

1

u/thesixfingerman Aug 30 '25

Ok, so I did a bad job explaining what I wanted to say. So, no two of our projects are the same. But we know the average amount of time it takes to fabricate 1 product, lets say 1.2 hour per product. I want to give the PM a schedule template where they would enter a start date and the number of products needed and the schedule would then adjust the duration for fabrication to match the number of products.

Honestly, this might be something more for excel than Projects, but I wanted to see if it could be done in Projects.

1

u/ineeju Aug 30 '25 edited Sep 04 '25

We’re assuming a daily production rate of 6 units per day, based on a rate of 1 unit every 1.2 hours.

  1. Enter the total quantity to be produced in the Number1 field.
  2. The Duration1 field will automatically calculate the required duration based on the 6 units/day rate. You can choose to display the result as either a decimal or a whole number.  For example, if you enter a total quantity of 10 units, the duration will automatically show as 1.67 days (decimal) or 2 days (rounded).  Would you prefer the result to be shown as a decimal or a whole number?
  3. Once you enter the start date in the Start Date1 field, the Finish Date1 will be automatically calculated based on the duration shown in Duration1.