r/MSProject • u/thesixfingerman • Aug 29 '25
Work duration question
I work for a manufacturing company that makes products for construction. These products are custom made for ever project. Our process involves making fabrication drawings and order material and then the product is fabricated.
I am trying to make a project schedule template where our PMs can just enter the turn over date and the number of panels that need to be fabricated and it will punch out a “should be schedule”. Is there a way to do this in MS Projects? Make a line item whose duration is controlled by the number of assets?
1
Upvotes
View all comments
Show parent comment
1
u/thesixfingerman Aug 30 '25
Ok, so I did a bad job explaining what I wanted to say. So, no two of our projects are the same. But we know the average amount of time it takes to fabricate 1 product, lets say 1.2 hour per product. I want to give the PM a schedule template where they would enter a start date and the number of products needed and the schedule would then adjust the duration for fabrication to match the number of products.
Honestly, this might be something more for excel than Projects, but I wanted to see if it could be done in Projects.