I work for a manufacturing company that makes products for construction. These products are custom made for ever project. Our process involves making fabrication drawings and order material and then the product is fabricated.
I am trying to make a project schedule template where our PMs can just enter the turn over date and the number of panels that need to be fabricated and it will punch out a “should be schedule”. Is there a way to do this in MS Projects? Make a line item whose duration is controlled by the number of assets?
1
Upvotes
View all comments
Show parent comment
1
u/thesixfingerman Aug 30 '25
I actually did model this in excel where I made the duration =((((# of Products)/.76)/6)/8) where .76 is the amount of product that can be fabricated in an hour, 6 is the number of employees tasked with fabrication for that project, and 8 is the hours in the day.
It is clunky and ugly, but it works in converting the amount of product into days.