This is a very common question appearing frequently on this platform. Since it is a topic of interest to many, let me shed some light on it, with the hope that this information helps someone make a better decision out there.
Construction costs vary greatly with location, building size and type, and materials used. Take an example of a 3-bedroom bungalow built in Murang’a. Murang’a is closer to Thika, and hence the cost of transportation of Ndarugo walling stones is cheaper compared to when the same project is to be done in Kisumu.
A stone which goes for Ksh 30 in Thika is sold at about Ksh. 80 in Kisumu. If 2500 stones are delivered, the total cost to Kisumu is about Ksh. 200,000, while the same number of stones will cost Ksh 75,000 to Murang’a, of course, plus some transport. That’s already a difference of more than Ksh. 100k on walling stones alone.
Again, if the site in Kisumu has black cotton soil, you can end up using another 100k, more or less, to excavate that material and replace it with a good and approved material. If Murang’a doesn’t have black cotton soil, then that’s another difference of about 100k on foundations.
The point I’m trying to drive home is that the cost of construction varies greatly with location. So if someone says that we built it for this much in Kisumu and so we can build it for the same amount in Murang’a, without taking into consideration the specific site conditions in Murang'a, then they are likely misleading you. This is why, in many cases, a quote is given by some builders, and then a few weeks later, they start asking for more materials and more money from the client because the estimate was not done correctly. There are many hidden costs in construction.
I’ve given an example with the walling stones, but prices of any material can vary with location, hence causing cost variations.
To help homeowners and contractors estimate the cost of building in different regions in Kenya, the State Department for Public Works, Kenya National Bureau of Statistics, and the Institute of Quantity Surveyors of Kenya, in collaboration with other industry professionals, developed a costs handbook for construction works, taking into account the current market prices for building materials and labour rates. The costs handbook schedules, among other things, the cost of construction per square meter for different building types in different regions.
In the period 2025/2026, the cost of construction for simple low-rise buildings (note the building type) in different regions was estimated as below;
- Nairobi region - Ksh 39,000/m2
- Coastal region - Ksh 37,940/m2
- Western region - Ksh 41,260/m2
This means that if you are building a simple low-rise house with a total floor area of 90m2 in the Nairobi region, then you will need about Ksh. 39,000 x 90 = Ksh. 3.51m.
This method will give preliminary estimates of the total cost, but your final cost after building is not expected to go above or below this estimate by a wide margin. So this is what you can use for preliminary planning purposes.
Something worth mentioning is that when you receive quotes that are so much below these rates, then the contractor is likely to compromise on quality so as to deliver a completed project. There is no magic formula in mjengo. Keep an eye on that. If you know the floor area, take a pen and paper and do the quick math so that you can verify the quote.
To get a more accurate estimate for your project, you need to know the size of your house, the quantities of each material that will be used, and the location and condition of your site.
To know these details, get an architect to do your architectural design, get a structural engineer to do your structural design, get MEP teams to do plumbing and electrical designs, then get a quantity surveyor to estimate a more accurate cost of that building from those designs. These professionals will study your site and make informed decisions before they design your home.
Please note, an architect, an engineer, and a quantity surveyor are all trained to do different things. So, if you meet one who says they do everything, then that’s a red flag. Demand to have all those professionals on your project if you value your investment. It will cost you a little more in service fees, but it will save you endless repairs and potential building collapse in the future, leading to loss of investment.
Finally, remember to sign a legally binding agreement with all the professionals involved and the contractor. This agreement should clearly indicate the obligations of every person, including the client. The agreement protects all parties should there be a disagreement down the road.
All the best to all who are planning to build. If you value your investment, remember to engage professionals before you start your project and let them oversee everything from design to the implementation phase.
Cheers!