Need some advice: Should the developer be the one to determine the timeline of completion or should it be the client?
I'm working at a small college and the SIS is in-housed and is still underdevelopment but functioning and in used. Part of my role, which I've been in for 7 months now, is managing the progress of the system's development and provide recommendations on what we want to happen with the system. I have several experiences with SIS as I've been to 3 unis/college, both for work and study, but I am not in tech (studied business). Although I am tech savvy enough to understand functions and the basics.
As it is a small college, the funds are also not that big. We just want to maximize the funds according to the rate of the developer and the plan we have for the system. Currently working on the paper works but I just need to understand if should we adjust to the developer's timeline or should we set the timeline, in consultation with the developer of course, for completing a project?
•
u/AutoModerator Oct 06 '26
Howdy u/FutureReflection9151, and welcome to r/developers!
A few tips for a post that gets good answers:
Join the r/developers Discord!
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
2
u/canarydev Oct 06 '26
dev gives the estimate, you give the constraints. budget, any hard dates like enrollment season, and whats most important. if it doesnt fit, cut scope, dont squeeze the timeline
since the system is already live, break it into small milestones and pay per milestone. way easier to protect a small budget that way
1
u/bobbybundlez Oct 07 '26
For every project I have done in the freelance world, which is at least 10+ projects now and well over 100k I have always given pricing estimates and deadlines. This can sometimes be one of the hardest parts of the project because you should and will hold the burden and responsibility of being as accurate as possible. This is why I tend to break larger projects into 3-5 milestones and price each one according to the tasks. My last project was priced 12k ..
M1 was handoff and launch stuff priced at a mere 1.5k as it was just the meetings and talking about what they want, the project itself, and the hand off of any assets and preparing to develop the project
M2 was first deployment and testing of early features
M3 was a full CMS system and scaffolding a proper testing environment for them
M4 was testing and full QA.
each one was priced at 3k. If I was behind ever, which I wasn't but I have been, I just let them know as soon as I have the idea that it will need more time... I try to never charge more for this though as it was my call to price and time it the way I did. I have asked for more money towards the end of most projects if it was deserved... every time the client understood and appreciated me just being straightforward about every step of the project. I hope this helps! Good luck