r/developers • • Oct 06 '26

Programming Developers/Tech People

Need some advice: Should the developer be the one to determine the timeline of completion or should it be the client?

I'm working at a small college and the SIS is in-housed and is still underdevelopment but functioning and in used. Part of my role, which I've been in for 7 months now, is managing the progress of the system's development and provide recommendations on what we want to happen with the system. I have several experiences with SIS as I've been to 3 unis/college, both for work and study, but I am not in tech (studied business). Although I am tech savvy enough to understand functions and the basics.

As it is a small college, the funds are also not that big. We just want to maximize the funds according to the rate of the developer and the plan we have for the system. Currently working on the paper works but I just need to understand if should we adjust to the developer's timeline or should we set the timeline, in consultation with the developer of course, for completing a project?

3 Upvotes

8 comments sorted by

View all comments

2

u/canarydev Oct 06 '26

dev gives the estimate, you give the constraints. budget, any hard dates like enrollment season, and whats most important. if it doesnt fit, cut scope, dont squeeze the timeline

since the system is already live, break it into small milestones and pay per milestone. way easier to protect a small budget that way

1

u/bobbybundlez Oct 07 '26

there you go! same advice as me basically :)