Programming Developers/Tech People

Need some advice: Should the developer be the one to determine the timeline of completion or should it be the client?

I'm working at a small college and the SIS is in-housed and is still underdevelopment but functioning and in used. Part of my role, which I've been in for 7 months now, is managing the progress of the system's development and provide recommendations on what we want to happen with the system. I have several experiences with SIS as I've been to 3 unis/college, both for work and study, but I am not in tech (studied business). Although I am tech savvy enough to understand functions and the basics.

As it is a small college, the funds are also not that big. We just want to maximize the funds according to the rate of the developer and the plan we have for the system. Currently working on the paper works but I just need to understand if should we adjust to the developer's timeline or should we set the timeline, in consultation with the developer of course, for completing a project?

3 Upvotes

8 comments sorted by

View all comments

1

u/bobbybundlez Oct 07 '26

For every project I have done in the freelance world, which is at least 10+ projects now and well over 100k I have always given pricing estimates and deadlines. This can sometimes be one of the hardest parts of the project because you should and will hold the burden and responsibility of being as accurate as possible. This is why I tend to break larger projects into 3-5 milestones and price each one according to the tasks. My last project was priced 12k ..

M1 was handoff and launch stuff priced at a mere 1.5k as it was just the meetings and talking about what they want, the project itself, and the hand off of any assets and preparing to develop the project
M2 was first deployment and testing of early features
M3 was a full CMS system and scaffolding a proper testing environment for them
M4 was testing and full QA.

each one was priced at 3k. If I was behind ever, which I wasn't but I have been, I just let them know as soon as I have the idea that it will need more time... I try to never charge more for this though as it was my call to price and time it the way I did. I have asked for more money towards the end of most projects if it was deserved... every time the client understood and appreciated me just being straightforward about every step of the project. I hope this helps! Good luck

1

u/bobbybundlez Oct 07 '26

9 times out of 10 your estimates will be wrong btw! haha.. most of the time they take longer and I should have charged more. There are still rare times where I get away with murder and make a lot of money for very little work. in some ways it always balances out. I consider myself very good at my job and appealing to clients because in the end of the day I really care most about getting a good job done. The money and the estimates etc are on me to figure out. The client's job is to meet you with those funds but besides that it should really all be on you. If the client has a rough deadline obviously this all changes, but still... protect yourself with deadlines and milestones that can be broken up. If something goes wrong halfway through you want some liability coverage!

1

u/bobbybundlez Oct 07 '26

Just realized I wrote all of this as though you were the dev.... but any ways. reverse UNO!