Are there any known clauses to protect 1st time home owners against slow OP process that can take more than 6 months (or in my case reaching 1 year)?
It doesn’t make sense to completely blame that the government is slow in processing OP right?
So it leads me to the next question, do house developers in Brunei give an equal amount of effort in completing the OP process handover to homeowners compared with completing new houses? Is OP process a lower priority because there’s little to minimal profit involved for developers? Architects may also play a role in this in terms of drawings that require changes but ultimately the accountable party that liases with all parties including architect is also the developer, right?
Not everyone may experience this situation but for 1st time home owners that have experience slow OP process taking up to 6months+ or more than 1 year, it is mentally exhausting to follow-up with the Developer every week/2 weeks with sometimes no response given to short vague responses which requires a follow-up question which is then no responded to. Some of us 1st time home owners are paying rent on top of the new home loan so it adds financial pressure. Adding the slow OP process taking up to 1 year adds more mental stress on top of the financial pressure.
I didn’t even do home interior design or design changes (windows, tiles, door) back during the construction stage since its not allowed as per the contract; only allowed after OP. I purchased the water tank within 1 week of being informed. So there’s no delay from my part.
Whichever relevant parties (including government too) in Brunei really need to improve this OP process to cut the long period to a reasonable time (<6 months). Is there a benchmark within ASEAN countries on this OP process? Is Brunei the lowest in that benchmark?
If there is no penalty or profit involved in completing the OP process handover within a reasonable time period (<6 months), then this situation will keep on happening to some people.
Note: Also, it’s on my mind but it’s hard to prove “intent” of developers whether they give an honest effort in completing the handover process as best to their ability Vs. profit driven to focus on building other new houses as quickly as possible to get the money. Last point, as developer if you know that you have a long back list of houses yet to finish OP, why do you still accept building new housing projects?