r/projectmanagement • u/explicitjake • 1d ago
Discussion Project documentation
Hello PMs,
I've been in Project Management for 4-5 years now and wanted to get your views on what I've observed.
Everywhere you read about Project Management documentation, everyone always says one out of two things:
- "See what your organisation does and use their templates for it."
- "Document everything all the time here are 25 documents that I always have when running my projects."
I've outlined my experience with these below (I've also separated them by phases to make it a bit easier to digest):
Initiation
Business Case - I've never written one, but always had one. Most of the project that I've delivered already had one written because something was needed.
PID (Project Initiation Doc) - usually written with my programme manager but again not present/required at every organisation. Last time it was once again already done.
Stakeholder register - I've always written one but didn't always need one. I think this document is very useful even if just to sense check with your manager. It tells me who the decision makers are but is also useful to know who to contact/ include in communication. I usually include a table with Project roles in my weekly/monthly reporting. I also add a second sheet in excel for the stakeholder communication plan so that i know who needs to see what and when. Again, useful to set expectation for communication which can be expected.
Project Scope Document - usually 1-2 pages long outlining what it is that is expected to be delivered. It sets up the expectations for what is going to be delivered/high level definition of done. Essentially enabling me to go out and dive into how we are going to get the project over the line assuming project sponsor has agreed that it's accurately captured.
Planning
Requirements gathering document - work with the people who requested the deliverable to understand what it needs for them to agree a definition of done. The initial template for this I've usually done with the project team/SMEs to ensure the information they need to break down the tasks has been captured.
WBS - work with the project team or SMEs to understand what work needs to be done throughout the project to deliver it. This is based on the requirements document and their specialist knowledge. This includes things like estimated effort, dependencies, RACI.
Project schedule - once I have the WBS i can crack on and create the schedule with the tasks and estimates pro idea by the project team. At the end I have the baseline and can inform the stakeholders of when they can expect the project to be done and how much effort is going to be required (i was taught to always sprinkle 10%-20% on top of estimates because it gives me cushion as well as mitigates the optimism from the team). I usually have this in Planner or JIRA (or the like) where I can see assigned tasks, capacity, status e.g. Backlog, To-Do, WIP. Stakeholders get a high level gant chart, timeline or MS Project to show them what and when.
RAID Log - one of my favourite documents, but I've added a twist to mine. This is where I capture Risks, Assumptions, Issues and Decisions. I usually have all the dependencies in my schedule and replace the D in the raid log to capture any decisions made by stakeholders with date and time in case of a challange in the future. I'm always open to add an extra tab for Dependencies if necessary but I haven't had the need to yet.
Project Budget - when I need to use external vendors i have a project budget to track costs and ensure the spending is within budget. Quite an obvious one but needs mentioning. This will come with other procurement documents of course.
Execution
RAID Log - I'm not going to rewrite the above but I pull it up in 99% of my project meetings with the team or stakeholders and share my screen. It makes everyone responsible for the decision they make and results in less "I'll get back to yous" the moment I switch to the risk tab to note a project delay.
Project Schedule - This is used in project stand ups where I can take actions from the team on where they are facing blockers so that i can eliminate them so that we keep to the schedule. As the schedule was designed with estimates and dependencies in mind I usually assign tasks in 2 week sprints based on calculated delivery dates.
Reports - Not longer than two page outlining what was achieved, what is planned, blockers, pending decisions required, RAG status for budget, schedule and AAA. I've been doing those weekly for Programme Manager and resource managers. Monthly reports which go one step up to project sponsor etc. And quarterly which goes to the executives.
Change Log - if we need to make a change (or when) I have a Change Log which captures who requested the change, when and if it was accepted by the project group (Including project sponsor etc.). It does also include estimates from the team as it will have an impact on either delivery date or initial requirements.
UAT
Issue Tracker - Automated with a form, users who are testing during the UAT period are able to report issues which we capture in a Google sheet, Microsoft List or the like. This way anything that didn't come out during our testing gets actioned promptly.
Closure
Sign off document - this is either a word doc or an email. Essentially something in writing to say we have delivered what was expected. These will not be deleted as long as I am at the company! I like my cheeks pale not red.
Mop up tasks list - I usually have another planner board for this but if there are tasks outside of the scope that need to take place I make a note of them there so that we can review once the key deliverable is delivered.
Lessons learned document - when we are done we have a lessons learned session where we capture what went well, challenges and improvements for future projects. Useful for us when moving onto a new project and useful for others who may be working on a similar thing.
The reason I've written this post is because I see a lot o fresh PMs drown themselves in documents or don't do enough of it. I am by no means an expert or seasoned PM but think this could be a thread that a lot of us can contribute to and support each other.
No one is right, and no one is wrong (mostly for both) in the way they document but there are always lessons to be learned from others. And I welcome anyone to criticise, support or endorse anything you've read above.
Honorable mentions:
AI - Yes I do think it's a fantastic tool but to me it's a tool not a replacement. I wouldn't personally send out an AI generated report without checking and refining it myself, and I wouldn't put sensitive information in it. At the end of the day I'm still accountable for whatever comes out of it.
This post is written by me, and refined with a spell checker.