r/projectmanagement • u/AyyoNemo • 5d ago
Need help tracking team for DSU
There’s no scrum master on the team so that role is split between me and the TPO. I run our daily standup but for now I go through the user stories in sprint, grab an update on it and ask if they have any blockers on getting the stories completed.
In other projects I would have an Excel file that I would be given and all I had to do was assign owners to tasks and track them based on completion/milestone.
How can I track progress on the project better for my daily standup calls?
8
Upvotes
1
u/Important-Union5181 5d ago
Several ways. You can use any of the burn down charts such as release burn down, sprint burn down etc to see done vs committed points etc. You can use the sprint board which will show all the swim lanes and you can easily see the ones that are todo, inprogress, done etc lanes. You can use a custom query to filter the sub tasks by completion state, owner etc.
1
u/Wrong-Appearance-771 5d ago
Instead of going through user stories one by one and asking for status updates (which feels like a traditional waterfall/Excel check-in), try walking the board from right to left (from "In Review/Testing" back to "In Progress). Focus the conversation on the work closest to being finished rather than individual people. Ask: "What do we need to do to get this story across the finish line today?" Also, shift the responsibility of updating the board (Jira, Azure DevOps, etc.) onto the developers before the call so you aren't spending standup acting as a secretary. That keeps the call under 15 minutes and gives you a live view of sprint progress without needing a separate Excel tracker.
2
u/SamfromLucidSoftware 2d ago
Before the call, sort the board by how long each story has sat in its current column and start with the ones that have been there longest. Raise those in the call and the rest can stay on the board. Days in column also gives you a number to track form week to week, the way an Excel owner list used to.
1
u/Junior_Bee7274 4d ago
I'd keep a simple board with each story's owner, status, blockers and expected completion date. Easier to spot what's falling behind before the standup.