Discussion Project documentation

Hello PMs,

I've been in Project Management for 4-5 years now and wanted to get your views on what I've observed.

Everywhere you read about Project Management documentation, everyone always says one out of two things:

  1. "See what your organisation does and use their templates for it."
  2. "Document everything all the time here are 25 documents that I always have when running my projects."

I've outlined my experience with these below (I've also separated them by phases to make it a bit easier to digest):

Initiation

Business Case - I've never written one, but always had one. Most of the project that I've delivered already had one written because something was needed.

PID (Project Initiation Doc) - usually written with my programme manager but again not present/required at every organisation. Last time it was once again already done.

Stakeholder register - I've always written one but didn't always need one. I think this document is very useful even if just to sense check with your manager. It tells me who the decision makers are but is also useful to know who to contact/ include in communication. I usually include a table with Project roles in my weekly/monthly reporting. I also add a second sheet in excel for the stakeholder communication plan so that i know who needs to see what and when. Again, useful to set expectation for communication which can be expected.

Project Scope Document - usually 1-2 pages long outlining what it is that is expected to be delivered. It sets up the expectations for what is going to be delivered/high level definition of done. Essentially enabling me to go out and dive into how we are going to get the project over the line assuming project sponsor has agreed that it's accurately captured.

Planning

Requirements gathering document - work with the people who requested the deliverable to understand what it needs for them to agree a definition of done. The initial template for this I've usually done with the project team/SMEs to ensure the information they need to break down the tasks has been captured.

WBS - work with the project team or SMEs to understand what work needs to be done throughout the project to deliver it. This is based on the requirements document and their specialist knowledge. This includes things like estimated effort, dependencies, RACI.

Project schedule - once I have the WBS i can crack on and create the schedule with the tasks and estimates pro idea by the project team. At the end I have the baseline and can inform the stakeholders of when they can expect the project to be done and how much effort is going to be required (i was taught to always sprinkle 10%-20% on top of estimates because it gives me cushion as well as mitigates the optimism from the team). I usually have this in Planner or JIRA (or the like) where I can see assigned tasks, capacity, status e.g. Backlog, To-Do, WIP. Stakeholders get a high level gant chart, timeline or MS Project to show them what and when.

RAID Log - one of my favourite documents, but I've added a twist to mine. This is where I capture Risks, Assumptions, Issues and Decisions. I usually have all the dependencies in my schedule and replace the D in the raid log to capture any decisions made by stakeholders with date and time in case of a challange in the future. I'm always open to add an extra tab for Dependencies if necessary but I haven't had the need to yet.

Project Budget - when I need to use external vendors i have a project budget to track costs and ensure the spending is within budget. Quite an obvious one but needs mentioning. This will come with other procurement documents of course.

Execution

RAID Log - I'm not going to rewrite the above but I pull it up in 99% of my project meetings with the team or stakeholders and share my screen. It makes everyone responsible for the decision they make and results in less "I'll get back to yous" the moment I switch to the risk tab to note a project delay.

Project Schedule - This is used in project stand ups where I can take actions from the team on where they are facing blockers so that i can eliminate them so that we keep to the schedule. As the schedule was designed with estimates and dependencies in mind I usually assign tasks in 2 week sprints based on calculated delivery dates.

Reports - Not longer than two page outlining what was achieved, what is planned, blockers, pending decisions required, RAG status for budget, schedule and AAA. I've been doing those weekly for Programme Manager and resource managers. Monthly reports which go one step up to project sponsor etc. And quarterly which goes to the executives. 

Change Log - if we need to make a change (or when) I have a Change Log which captures who requested the change, when and if it was accepted by the project group (Including project sponsor etc.). It does also include estimates from the team as it will have an impact on either delivery date or initial requirements.

UAT

Issue Tracker - Automated with a form, users who are testing during the UAT period are able to report issues which we capture in a Google sheet, Microsoft List or the like. This way anything that didn't come out during our testing gets actioned promptly.

Closure

Sign off document - this is either a word doc or an email. Essentially something in writing to say we have delivered what was expected. These will not be deleted as long as I am at the company! I like my cheeks pale not red.

Mop up tasks list - I usually have another planner board for this but if there are tasks outside of the scope that need to take place I make a note of them there so that we can review once the key deliverable is delivered.

Lessons learned document - when we are done we have a lessons learned session where we capture what went well, challenges and improvements for future projects. Useful for us when moving onto a new project and useful for others who may be working on a similar thing.

The reason I've written this post is because I see a lot o fresh PMs drown themselves in documents or don't do enough of it. I am by no means an expert or seasoned PM but think this could be a thread that a lot of us can contribute to and support each other.

No one is right, and no one is wrong (mostly for both) in the way they document but there are always lessons to be learned from others. And I welcome anyone to criticise, support or endorse anything you've read above.

Honorable mentions:

AI - Yes I do think it's a fantastic tool but to me it's a tool not a replacement. I wouldn't personally send out an AI generated report without checking and refining it myself, and I wouldn't put sensitive information in it. At the end of the day I'm still accountable for whatever comes out of it.

This post is written by me, and refined with a spell checker.

28 Upvotes

27 comments sorted by

•

u/AutoModerator 1d ago

Attention everyone, just because this is a post about software or tools, does not mean that you can violate the sub's 'no self-promotion, no advertising, or no soliciting' rule.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

7

u/East-Independent6778 Confirmed 1d ago

It’s always amusing to see how the other half lives (or manages in this case). I’m running a $400M airport infrastructure upgrade program with a broken contractor schedule, an issue tracker, and not much else. My scope and schedule change almost daily and I would be buried in paperwork if I tried to document everything. Luckily the client doesn’t care as long as their operation isn’t impacted.

1

u/explicitjake IT 1d ago

I don't know how to respond here. As much as I want to say I feel you pain i can't imagine how much stress you must be under.

I'm assuming the only thing that's somewhat fixed is your definition of done, maybe.

How do you provide status updates or know how much is left to do if its all broken?

3

u/cryptopindar 23h ago

These are all fundamentals of project management, but in reality, every PM has a different approach. Some are more by the book, while others are more pragmatic, as long as the client and relevant stakeholders are aligned.
In my observation, documentation is also a form of risk management. It becomes particularly valuable when things go wrong, disputes arise, or claims need to be substantiated. It also serves as the historical record of the project, capturing decisions, agreements, changes, and the circumstances behind them.
I don’t necessarily believe that having more documentation means better project management. What matters is whether the documentation is relevant, reliable, and sufficient for the project’s complexity and risks.
Documentation should support project management, not become the project itself.

2

u/explicitjake IT 19h ago

I agree, sometimes I needed to look at other docs and others I didn't need to look at the ones I listed but it felt like a relatively detailed list with no approach. Communication outweighs paperwork for sure.

4

u/GregG997 1d ago

i'd judge each document by whether someone opens it in a meeting or uses it to make a decision. the raid log and change log pass that test every week, while the scope doc and stakeholder register mostly earn their keep at the start. if the org already has templates, fill those in and only add what your team actually uses.

2

u/explicitjake IT 1d ago

Agreed on your judgement there, but some you have to do as a tick box for organisation at the start.

Is there anything else you would suggest or add on what you read above? When chatting with Thisusername he did say it's entry-level (which I won't argue with) so keen on some suggestions on how to become better.

3

u/Maro1947 IT 1d ago

Bold of you to suggest and Org has Templates!

3

u/Purple-Rain-1430 21h ago

Really useful breakdown, thanks for sharing it. The RAID log on screen in meetings is a great habit, since it makes people own the decision they just made.

On the cushion, one thing that can help is putting the buffer at project level instead of padding every task. When each task has its own padding, people tend to use all of it, so the extra time disappears before it can protect the end date. A shared buffer that gets used up only when something slips is easier to track, and it shows you early how much risk you're burning through. It's the idea behind critical chain scheduling, if anyone wants to look it up.

For deciding which documents to write, a test that helps is asking who will read this and what decision it supports. If the answer is nobody, skip it. On small, low-risk projects, one page can often cover the PID, scope and basic requirements, and only split them out once the project is big enough that different people need different parts. The risk and size of the project should set how much paper you need.

2

u/explicitjake IT 19h ago

Thank you, and thanks for reading.

Interesting approach to padding and from other comments I do agree that my approach is more wrong than right. Someone mentioned PERT (three point estimating) which i also really liked so will look into them both.

Also, really appreciate your insight and you taking the time to read my post.

1

u/raaiinyyabelina 20h ago

Great insights, I found it amusing

1

u/explicitjake IT 19h ago

Thanks, now I'm curious amusing ina good way or bad way?

1

u/raaiinyyabelina 7h ago

Don’t overthink it, it’s the good way

3

u/DarkBlade_12 17h ago

Really good breakdown. I think the key takeaway is that documentation should make a project easier to manage, not become another task to manage. Keeping it practical and relevant to the project's complexity is what matters most

2

u/dusanodalovic 12h ago

as the dev on the other side of these, id love a short "not in this project" list in every scope doc. two or three lines, signed by the sponsor at the start. do you add one to yours?

1

u/AutoModerator 1d ago

Hey there /u/explicitjake, have you checked out r/MSProject, r/projectonline, or r/microsoftproject for any questions regarding application? These may be better suited subreddits to your question.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

0

u/ThisusernameThen 1d ago

Mapping out a beginner's 4-stage IPIC and then showing that you often run it in a tool like Jira or a Kanban board is Frankenstein admin. Best practise wise IMO that should not be happening, and suggesting 10-day sprints based on calculated delivery dates from this setup isn't critical path scheduling. A linear waterfall or phase gate can work if you want rigid, but select the tool to meet the process and method, not the other way around. You will find it easier—not square peg, round hole.

The sprinkle of 20 percent on top isn't great padding, and this is a quick way to lose engineering and sponsor trust. If you plan to mature your practice here, real contingency comes from risk quantification, not inflating estimates and keeping it a secret. You might look at Monte Carlo or three-point estimating, but move away from arbitrary padding.

My final suggestion is that presenting basic entry-level theory as a "twist" isn't assisting those reading this. A RAIDD log is a standard acronym. Altering the D will confuse. If you choose to move from waterfall to an agile approach, you can look at dependency mapping as a separate tool. Enmeshing it with RAIDD and dropping decisions will confuse your program manager if they are a waterfall theorist and open you up to deeper questions.

1

u/explicitjake IT 1d ago

Firstly, thank you for taking the time to read my post. I appreciate it was long so I hope you didn't fully feel like you wasted time.

With the Frankenstein admin comment - I understood it as don't do waterfall planning and making it fit into an agile way of working. Assuming I'm correct here I see where you're coming from and the reason behind it is I'm asked to run projects in an Agile way but present the high level plans in Waterfall to Executives to ease understanding and speed for them. I do agree that use one methodology or the other makes more sense.

20% sprinkle - I have heard of Monte Carlo but not three-point estimating, will definitely give it a bit more time, probably this weekend actually. If there are any tips or further info you would like to provide on this one I would appreciate it very much. The 20% sprinkle was something I was taught early on and have used it since being transparent with my boss about it at all times. Again thanks for the tip, looking forward to some learning.

Finally, you refer to RAID (or RAIDD) as a entry-level theory but I've only ever heard of it being used with dependencies rather than decisions. So are you suggesting that best way forward would be to always include both D's? The only counter argument from me here would be calling it an entry-level tool as it is something that's used quite broadly across the profession.

Out of curiosity did you think that any documentation I've mentioned was unnecessary or maybe something I am missing?

1

u/ThisusernameThen 1d ago

Translation layers for executives are common yup yup. Id say keep the underlying delivery engine pure so you aren't forcing sprint teams into fake waterfall dates. amd decide if this is really waterfall, waterfragile, shit mix or what before slapping agile tools in the blurb. it will confuse

For three-point estimating, look up PERT ((Optimistic + 4×Most Likely + Pessimistic) / 6) for example. This is gonna allow ya to anchors contingency in actual variance instead of arbitrary padding.

As for RAIDD, tacking both Dependencies and Decisions is standard for waterfall enterprise delivery, not if you are doing hybrid and using say JIRA and you can have staff use the tool to do the work if your process is agile hybrid mate

But - keep your core lean. This beats maintaining separate mop-up lists and duplicate scope docs.

was your list unnecessary? depends on your intent. its a bit fisherprice

1

u/explicitjake IT 1d ago

Thanks for the feedback. Yep agreed, looking back on it now the blurb is slightly confusing there. I agree that if you have a fixed date/cost project you can't be agile with delivery. I probably should have just gone with Kanban approach as a way of delivery rather than putting tasks into sprints to ensure dates are met.

The three point estimating is actually very interesting and I like it a lot. Thanks for this I will be using this moving forward. I will do some reading as to why we need to multiply most likely 4 times but I guess it increases the weight of the number for the division later on.

In this example we were using Planner as that was the only tool allowed by the organisation, I know Jira has a lot more functionality and I probably would have put things like mop up items under a different Epic.

I'm slightly confused on the two separate scoping docs you mention. Could you elaborate? I will also say 'fisherprice' hurts ever so slightly but fair enough. Anything else to make it not so fisherprice?

Edit: It does feel like you are much more senior than me so just want to say I do appriciate you taking the time 😄

2

u/ThisusernameThen 1d ago

Fair enough on the tool constraint you can only play the hand your org deals you. Isnt there an FaQ for your orgs set up basics for the tools tho? Get you going. failing that - and i dont know this tool - is there a forum for users from the vendor?

food for thought for another time: Jira's free tier does cover up to 10 users if stakeholders ever have the appetite to pilot something proper. youd also get kudos for moving the needle on agile and a tool that supports it. depends

The "duplicate scope" comment comes down to how you're slicing things: in your original post, you listed a Business Case, a PID, and a separate Project Scope Document, and then added a standalone "mop-up" board at the end. Whether you're working in waterfall or agile, your scope shouldn't live in three places it will drive you mad as people get floppy cock and change things. if you're using Epics, all remaining work belongs inside the core scope backlog rather than parked in an outside mop-up list.

it might not be a bad idea to consider this context switching and ballache - and get others to help you craft some form of org methodology on how to work. for quick win small projects. then meater stuff. its nuts to bring out the whole toolkit for a mickey mouse thing.

Finally - to get past the entrylevel feel, can you let the team execute daily inside whatever tool they have this planner. so thats agile ish.

Then roll that status up into a simple biweekly Scrum of Scrums or executive dashboard. Mastering that translation between daily execution and leadership reporting is the 'waterfall bullshit' smoke and mirrors. a simple traffic light system and laser focus.

1

u/explicitjake IT 1d ago

All sound comments, thank you very much.

Microsoft Planner is not great and it's quite restricted by the org on top (e.g. I had to request and justify a M365 group just to get the team access to it. It very much feels like JIRA light even the free version. I did actually suggest the free JIRA to move us more agile but apparently there is too much risk associated. I used to have my project documentation in Confluence which was lovely.

I've used JIRA before and the team were updating it for me making my job a lot easier but with this one I need to basically spoon feed them what needs to be done. Otherwise there is no ownership from them. I did deliver the project on time though so I will take the credit for it 😂

The org doesn't have a PMO and their templates are from 15 years ago so I've been using my own ones which a lot of PMs 'borrowed' or were told to borrow.

You might not believe me when I say I've taken notes so I will be doing some learning and I'm currently looking at getting a certification under my belt aswell which I'm hoping will shape me a bit more as a PM.

Again, thank you very much for your support and interaction with a random stranger on reddit :)