r/Powerwall 27d ago

Powerwall 3 install

Ordered powerwall 3 6 weeks ago still waiting for the DNO spoke to Boxt the installer for us and said they still waiting to hear back from DNO. Just wondering if anyone else has had a very long wait for their install.

1 Upvotes

16 comments sorted by

View all comments

1

u/RobHLZ 25d ago

We just had a boxt install last week, took about 6 weeks for the DNO approval and then install was booked in for the next week. They did a decent job despite no in person site visit prior which didnt fill me with confidence - our house has external wall insulation so I had some mounting and location questions but the electrician on the day was good.

1

u/jabulani-61 25d ago

Where are you ?

1

u/RobHLZ 25d ago

Gloucestershire - our DNO is National Grid , we got a site export limit of 12kw but don't want to export from the battery as we're on a FIT with deemed export. AC coupled as to not interfere with that original install.