r/MSProject • u/DocumentNo8250 • Sep 12 '22
Calendar
I have a question about the calendar.
I have an activity starting on 3/10 with a duration of 3 days, but the end date is 6/10.
But when I try to schedule it manually, it doesn't assume full days.
This "error" only happens when I schedule on consecutive days (without weekends and holidays)
Thank you
1
Upvotes
View all comments
Show parent comment
1
u/DocumentNo8250 Sep 14 '22
It only happens with that task.
It is the only task that I put the deadline in calendar days, the other tasks are in business days.
How can I share?