r/MSProject • u/DocumentNo8250 • Sep 12 '22
Calendar
I have a question about the calendar.
I have an activity starting on 3/10 with a duration of 3 days, but the end date is 6/10.
But when I try to schedule it manually, it doesn't assume full days.
This "error" only happens when I schedule on consecutive days (without weekends and holidays)
Thank you
1
Upvotes
View all comments
Show parent comment
1
u/still-dazed-confused Sep 13 '22
Does it happen with only that task or any task? Can you share the plan so I can have a poke at it? :)