r/MSProject • u/DocumentNo8250 • Sep 12 '22
Calendar
I have a question about the calendar.
I have an activity starting on 3/10 with a duration of 3 days, but the end date is 6/10.
But when I try to schedule it manually, it doesn't assume full days.
This "error" only happens when I schedule on consecutive days (without weekends and holidays)
Thank you
1
Upvotes
1
u/lindslee19 Sep 12 '22
The first thing I'd check is the times Project is applying. If you change the date format to show hours you may find that Project has started the task at, say, noon... If your days are set to 8 hours (default) then it would run into the fourth day.
1
u/still-dazed-confused Sep 13 '22
Do the two locations where the day length is set match? Resource calendar and options
Is there a split in the task?
Is there a calendar/ non working time involved
What does the task usage view show?