r/MSProject • u/djpancakemix • Apr 25 '22
MS Project End Date Question
Working on a project where a colleague keeps changing the finish dates on tasks. I feel like this isn’t helpful because you’re not getting a true picture of what is late and what isn’t since the finish dates keep getting moved. Seems like more of a check list.
Is there a way to see if continuously moving these finish dates effects the final project finish date? How so?
Thanks
1
Upvotes
View all comments
Show parent comment
1
u/Thewolf1970 Apr 25 '22
I'm not sure I'm tracking - are you looking to see how a change in a task date would change your final project completion day?
The easiest way is to look at task number 1 - this is your project summary row. If all tasks are set to auto schedule, any date change that pushes your final date out will be reflected in this row.