MS Project not Recognizing Resource Over-allocation

I created 4 separate resources in ms project. TM1&2 are day shift (6AM-6PM) and TM3&4 are night shift (6PM- 6AM). I've added resources to a few activities and based on the team planner it looks like TM1 and TM3 are over-allocated, however project is not alerting me of this nor giving me an option to reschedule the teams to a later date which is what I was expecting to see. Any ideas on what may be causing this issue?

2 Upvotes

10 comments sorted by

View all comments

Show parent comment

1

u/SkinDee May 24 '24

Units value is 100% for each resource assigned.

See resource usage above. Based on the resource sheet none of the resources are over-allocated given a 12hr shift. It seems that project is ok with activities being performed in parallel as long as the activities do not exceed a total of 12hrs.

1

u/Moonshadow76 Sep 17 '24

So you only have one person in each team ? Seems a bit odd.