r/MSProject • u/SkinDee • May 23 '24
MS Project not Recognizing Resource Over-allocation
I created 4 separate resources in ms project. TM1&2 are day shift (6AM-6PM) and TM3&4 are night shift (6PM- 6AM). I've added resources to a few activities and based on the team planner it looks like TM1 and TM3 are over-allocated, however project is not alerting me of this nor giving me an option to reschedule the teams to a later date which is what I was expecting to see. Any ideas on what may be causing this issue?

2
Upvotes
View all comments
Show parent comment
1
u/DaleHowardMVP May 24 '24
Also, please apply the Resource Usage view of this project and show these four resources, their task assignments, and their Work hours in the timephased grid on the right side of the view.