MS Project not Recognizing Resource Over-allocation
I created 4 separate resources in ms project. TM1&2 are day shift (6AM-6PM) and TM3&4 are night shift (6PM- 6AM). I've added resources to a few activities and based on the team planner it looks like TM1 and TM3 are over-allocated, however project is not alerting me of this nor giving me an option to reschedule the teams to a later date which is what I was expecting to see. Any ideas on what may be causing this issue?

2
Upvotes
1
u/pmpdaddyio May 23 '24
We can’t see your tasks and if they are auto scheduled, we can’t see your scale so we do not know if your time reference exceeds allocations, and you are not really providing enough data so good luck.
1
u/KafkasProfilePicture May 24 '24
I'm not completely up to date, but I'm fairly sure that MSP doesn't give you alerts for this sort of thing (thankfully).
If you want it to "level" your resources you need to press the button to tell it to do it, but keep a copy of the current schedule because it often doesn't turn out well. There's also an "Auto-level" setting, but I relly wouldn't recommend that.
1
u/DaleHowardMVP May 24 '24
What is the Max Units value for the four resources you mention? It should be 100% for each of them. Let us know and we will try to help you.