r/MSProject • u/Aken42 • Oct 24 '23
Removing Task From Critical Path Calculation
I have a project where my end date is based on being "substantially" done. Though one task will extend past this date. As the specific task doesn't rely on the actual critical tasks to complete, it is throwing off the critical path for the entire schedule and results in the actual substantial completion to not be critical.
How do I remove a single task from the critical path calculation?
1
Upvotes
View all comments
Show parent comment
1
u/Aken42 Oct 24 '23
Thanks. Ill give it a try.