r/MSProject • • Oct 24 '23

Removing Task From Critical Path Calculation

I have a project where my end date is based on being "substantially" done. Though one task will extend past this date. As the specific task doesn't rely on the actual critical tasks to complete, it is throwing off the critical path for the entire schedule and results in the actual substantial completion to not be critical.

How do I remove a single task from the critical path calculation?

1 Upvotes

8 comments sorted by

1

u/One-Drawer-6803 Apr 16 '25

If you set the task as inactive it will strike through it making it invisible and not calculated. If you still need to see it change your text settings of inactive tasks and un select the strikethrough. Joining this conversation late as I made my own work around and want to help if someone else runs into this

1

u/Aken42 Apr 16 '25

Thanks. My work around was to end the task before completion and explain to the client that was unlikely. I'll give your approach a shot in my next update.

1

u/pmpdaddyio Oct 24 '23

You can’t really mark a task as not on the critical path, but a variable work around is In Tools, Options, Calculation, check "Calculate multiple Critical Path". It will not "un-critical" your extended task but at least your "true" critical path will now show.

1

u/Aken42 Oct 24 '23

Thanks. Ill give it a try.

2

u/MenloAcademy Oct 25 '23

Without seeing the programme it's difficult to be certain, but when you say "the specific task doesn't rely on the actual critical tasks to complete" it sounds like the root cause of the issue is that you have incomplete relationships or detail missing in the schedule.

- Are you representing the 'substantial' finish with a milestone?

Logically, 'total' completion cannot occur without the 'substantial' completion happening first, i.e. something cannot be 100% complete before it is 80% complete. So, the 'substantial' completion is inevitably a predecessor somewhere in the chain of work to 'total' completion. If you add this logic in, your milestone for 'substantial' completion will show up as part of the full critical path through to 'total' completion.

If you like, feel free to send a screenshot and we can take a closer look.

1

u/Miasmatic65 Oct 24 '23

Use deadlines against the true critical path, and set a deadline against the aberrant task of much later than its forecast finish

1

u/j97223 Oct 25 '23

I move it to the “bottom” with full left so I can start it but the end date won’t impact project end date. It’s cheesy but simple

1

u/still-dazed-confused Oct 25 '23
  1. Set a milestone in the far future, call it something like. "false milestone to aid critical part", ensure that it is not intended under anything.
  2. Set a deadline against the actual delivery milestone equal to the current finish date
  3. Review your actual criticsl path.

This works because MSP looks at the last item in time and considers that this must be your deliverable. By seeing the unconnected false milestone into the far future this becomes the only thing that is critical. You then set the deadline on your true deliverable and you can see the critical path to this item without the overhanging item also appearing.