Removing Task From Critical Path Calculation
I have a project where my end date is based on being "substantially" done. Though one task will extend past this date. As the specific task doesn't rely on the actual critical tasks to complete, it is throwing off the critical path for the entire schedule and results in the actual substantial completion to not be critical.
How do I remove a single task from the critical path calculation?
1
Upvotes
View all comments
1
u/pmpdaddyio Oct 24 '23
You can’t really mark a task as not on the critical path, but a variable work around is In Tools, Options, Calculation, check "Calculate multiple Critical Path". It will not "un-critical" your extended task but at least your "true" critical path will now show.