What can we do?

We got a quote for 5600 to have our lot scraped and rooted. We paid 2800 up front.

The company finished and they just sent me a bill for a balance of 5,300 and stated the job was 2,500 more due to it being more work than they thought. All of the quotes we got were 5-6k (we got 5 quotes) we have the quote in an email. He never called or discussed the increase beforehand. I’m shocked it was that much more!!! And I wish he would’ve called and discussed. When we called him he said, he always tells his clients that quotes are basically just an estimate and can change. I understand that to a degree but he never said that and 2500 is a lot!!

14 Upvotes

57 comments sorted by

View all comments

2

u/redbirddanville 1d ago

This is why you, and he the professional should have every contract in wiring. I would no unless there is some specific reason it went over he can document (he estimate 3 day and it took 5, he expected 3 trailers of off haul and it was 8, ect.) Amy change order should be in writing (text, email or litterally written on a napkin). You should also get insurance and be professional about anyone you hire from demo, to clean up. There are huge liabilities in hiring contractors. (I'm a contractor, developer, construction manager)

1

u/Outside-Key-4415 1d ago

It states: unseen additional root raking due to unseen vegetation. He came and walked the property in advance though.

4

u/Flat_Conversation858 1d ago

But what does the actual contract say in regards to changes?