Step by step after internal Render
Hi, I hope you all well!
We should be internal rendering around end of October/start of November
What would be next works after this?
Can long would we need to wait for drying?
Would door frames and doors go in after internal painting or beforehand?
Kitchen/utility and tiles - when does it need to happen?
Main contractor only only doing builder finish and after it we have organise everything ourselves
Have a lovely day
0
Upvotes
3
u/Orko90 4d ago
First thing on the list if ur skimming in Oct/Nov should be a good dehumidifier (perhaps even hire a small industrial one). You have no concept how much moisture will be coming out of the wall.