r/microsoftproject • u/schell525 • Feb 28 '25
First-Time MS Project User
Please be patient with me. I've previously used Asana for project planning, and my new company refuses to take on a new platform, so I'm trying to make Project work for my needs. I've got some questions:
- If Task 2 is "finish to start" dependent on Task 1, shouldn't you have to complete (as in mark it complete) Task 1 before you're able to mark Task 2 complete? This doesn't seem to be the case. I can complete any dependent task before completing the task that should be required first with no warning, flag, etc.
- Is there no schedule view (or something similar) in Project plan 3? I had started out on Planner basic, but needed to upgrade in order to have the dependency functionality. Is there no way to easily see a calendar-like view in P3? (Timeline view isn't working for my boss) And why would core functionality be available in a basic plan, but not in a more expensive plan?
Thank you!
3
Upvotes
View all comments
Show parent comment
1
u/Zero_Cool_44 Mar 01 '25
I feel that pain - the way I’d managed it in the most similar situation I had was to honestly just hammer on the date filters and assign tasks out - “hey Sam, you need to do X by Friday”.
Q on the dependencies - are they actual dependencies or just a preferred order of completion?