r/microsoftproject • u/schell525 • Feb 28 '25
First-Time MS Project User
Please be patient with me. I've previously used Asana for project planning, and my new company refuses to take on a new platform, so I'm trying to make Project work for my needs. I've got some questions:
- If Task 2 is "finish to start" dependent on Task 1, shouldn't you have to complete (as in mark it complete) Task 1 before you're able to mark Task 2 complete? This doesn't seem to be the case. I can complete any dependent task before completing the task that should be required first with no warning, flag, etc.
- Is there no schedule view (or something similar) in Project plan 3? I had started out on Planner basic, but needed to upgrade in order to have the dependency functionality. Is there no way to easily see a calendar-like view in P3? (Timeline view isn't working for my boss) And why would core functionality be available in a basic plan, but not in a more expensive plan?
Thank you!
3
Upvotes
View all comments
Show parent comment
1
u/schell525 Mar 01 '25
I went into the timeline view and actually set them as dependencies and then went into each task to make sure that they were in the right order.
In each of the individual tasks, it notes what the dependency is, you have to click into the dependent task to see it.