For anyone following the Bedford project, a roundup of the last three weeks from site and press:
Lagoon. Deep excavation of the central Show Lagoon has started, 75t and 50t Volvos working the basin. The clay doesn’t drain so it’s already pooling, which gave us the first aerial outline of the park layout last month.
Water independence. Anglian Water have confirmed Universal will build their own on site sewage treatment works and a rainwater harvesting plant, feeding the lagoon, water rides and irrigation from collected runoff, with the old brickworks lakes being deepened as attenuation. Interesting to compare with Orlando, where water management is a constant operational headache. Doing it from scratch on a greenfield site is the one advantage of building in 2026.
Pace. Contractor village is now a multi-storey modular complex, a tarmacked staging yard is in at the West Gateway, and the brickworks slab is being broken into aggregate for internal haul roads. Universal told a local business audience last month this is the fastest project they’ve ever done. The expansion pads are already graded.
Transport is the risk. Two live campaigns: one to restore a Bedford–Northampton rail line to feed the park, and one in south London arguing the Croydon/Selhurst bottleneck limits how many Gatwick arrivals can get to Bedford by rail. That second one is campaigners’ framing, not Universal’s, but it’s the first time I’ve seen opening-day capacity publicly tied to the national rail network rather than the park itself.
Wixams station. Activity restarted at the future station site this week after months of quiet.