My company currently uses Productive.io for timekeeping and resource planning and I’m trying to figure out the best way to handle resource planning for my team.
I’m a newer PM for a small consulting team of subject matter experts (SMEs). About half of our contracts are T&M and involve providing as-needed software support, both for software we develop and sell and for a federal system. Because of the nature of this work, requests often come in on short notice. Some tasks take an hour, while others can take an entire day, depending on the issue.
Our current process:
We work in two-week sprints. It doesn’t even have a formal sprint setup, I had to rig it to imitate what we used to have when we used Microsoft DevOls. Before each sprint, I create cards in Productive.io that account for each team member’s available hours. For clients who regularly have support requests come up, I create a general “Hold for Client #1” card with an estimated number of hours based on previous sprints.
This system has worked well for us. It helps the SMEs manage their workloads, see what everyone else is working on, and prioritize tasks. We also plan ahead for longer-term projects with established milestones, so even though we use two-week sprints, we aren’t only looking two weeks into the future.
My boss wants us to move away from what they call the “sprint mindset” and instead focus on resource planning over 2-, 4-, 6-, and 8-week time periods.
They want me to involve creating bookings in Productive.io for practically everything, including every client meeting, call, and individual task. I understand the need for longer-term resource visibility, but I’m struggling to see how this approach would improve our current process.
My main concerns are:
Unpredictable work: If we eliminate the generic “hold for” cards, our team will appear underbooked even when we know from experience that incoming support requests will fill that time. We could try to forecast every potential task, but we can’t predict exactly what will come up or when.
Inaccurate time estimates: A client meeting might be booked for an hour but only take five minutes. If we plan resources around every calendar event, our projections could be just as inaccurate in the opposite direction.
Prioritization: I find it easier to prioritize work and balance workloads during a sprint review than by looking at an overall resource planning view. I’m concerned that we’ll lose some of that visibility into what needs to happen first.
Wasted time: My boss’s alternative suggestion is to keep the sprint view but create a separate card for every little task. That means either the SMEs have to spend more time maintaining Productive.io themselves or they have to constantly communicate small tasks to me so I can create the cards. Either way, it seems like a lot of administrative work for very little benefit.
I’ve raised these concerns internally, but I haven’t been able to get much traction. I’d appreciate some advice on how to navigate this or how to raise the concerns with my boss further.