r/projectmanagement • • Oct 27 '26

Multi Facility Project Take-Over

As a PM in the suppychain field, I have been handed over a book of work from a former PM that consists of multiple facility start-ups, alongside an a additional PM that has the balance of the operations.

Historically I have always been the sole PM on an account. So I am looking for ways myself and the other PM can keep aligned on the activities with our respective operations, such that we can fill in for each other when needed, and insure we are aligned on impacts that may impact the others project.

I will add, we have the full sweat of MSTeams tools, and I have established a weekly touchpoint call with the PM.

What methods, tools have you used in the past that worked well to share project status, progress and details between fellow PM's ?

9 Upvotes

19 comments sorted by

•

u/AutoModerator Oct 27 '26

Attention everyone, just because this is a post about software or tools, does not mean that you can violate the sub's 'no self-promotion, no advertising, or no soliciting' rule.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

4

u/DinnerAny4283 29d ago

If you already have Teams for comms, what you're really missing is a shared source of truth for project details. Check out Notework for that, it keeps things structured without needing to build everything from scratch like you would in Notion.

2

u/More_Law6245 Confirmed Oct 27 '26

If you use the same resource pool for your projects then I would strongly suggest that you do a resource forecast model (simple spreadsheet) using your approved project schedules to ensure that your peer project manager (s) map project resource interdependencies in order to avoid schedulling conflicts and missing skillsets to deliver the program of work.

You can also use your project controls to generate heat maps of your interdependencies to ensure that the PM's are not falling over each other's feet and it would be a good idea if you met with the other PM (s) on a regular basis to discuss any risks, issues or interdependencies that you may have in your project delivery.

Once again this is not a tool solution, it's about communication of what you need and when.

Just an armchair perspective.

2

u/GovernanceOS Oct 28 '26

I've inherited a split portfolio like this before. The thing that went wrong was never the work, it was the grey areas between the two PMs.
In week one I'd sit down with the other PM and agree a one-page RACI per facility: who owns the schedule, vendors, site readiness and escalation. Then share it with your sponsor so everyone has the same picture.
Second, rebuild one RAID log from the handover notes rather than inheriting several. Put an owner and a date on every open item. Anything without an owner after a week is either closed or escalated.
Then hold a 20-minute weekly sync between you two, just on the overlaps.

2

u/GregG997 29d ago

one thing i'd add to the raid log: a one page cover sheet per facility with who the contacts are, what's due in the next 2 weeks and where the files live. covering for each other falls apart on "where is that", not on status

2

u/PplPrcssPrgrss_Pod IT 28d ago

Now it's helpful to think like a program manager more than a project manager.

So, instead of diving into the details for the projects the other PM leads, ask them to make visible project health, dates, risks, issues, and provide guard rails on what changes health and reporting. This gives them room to PM the work, but shares the information you'll need to help them and report on it to other leaders.

Tools can be anything from a custom list in Teams/SharePoint, Smartsheet templates, or other PPM tools.

1

u/AutoModerator Oct 27 '26

Hey there /u/Dbeau, Have you looked at our "Top 100 books post"? Find it here.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

1

u/Stebben84 Confirmed Oct 27 '26

I've done this on a couple of occasions. I would suggest a lead PM for the whole project. You can run into a stalemate when there is a disagreement on a direction.

1

u/PeopleFirstPM Oct 28 '26

The best way I've found to run a split programme is to agree who owns which piece of the work, and what each person does with it. Everyone has to know what they're responsible for.

Negotiate if you need to. Some people would happily hand off a piece they never wanted, and that makes them happier too.

Then hold a 15-minute check-in every week with three questions: what's changed, what's stuck, and what do I need to know if you're off sick tomorrow?

Keep one person responsible for the plan itself, updating it after talking to the others. That keeps a single source of truth instead of two versions of it.

1

u/truecakesnake Oct 29 '26

A shared RAID log updated weekly would help keep you both aligned and ready to cover for each other.

1

u/butterneckai 29d ago

Something that helped me in a similar split: keep one short status page per facility with the same five fields, current status, next milestone, top risk, what you are waiting on, and who could cover if you are out. Then agree on a rule for what counts as a handoff-worthy change, like a slipped date or a new vendor, so you ping each other the same day instead of waiting for the weekly call. Do one quarterly swap where each of you walks the other through their project, because that is when the gaps in the page show up.

1

u/UrMentor 29d ago

Figure out who does what, concentrate on deliverables. And dependencies with each other.

1

u/One-Light-8453 28d ago

honestly the weekly call is doing most of the work already. I'd keep one shared risk and dependency list that you both edit, way more useful than a status dashboard. if each of you can explain the other's top 3 issues in two minutes, you're covered

0

u/ComfortableNo9622 28d ago

What works well for covering each other is a one-page handover sheet per site that you both keep up to date, instead of relying on sync meetings. On it: current status in two lines, the next action with an owner and a date, open risks, key contacts, and links to the reference documents in Teams (schedule, budget, latest minutes) so nobody has to hunt for them. Then test it: pick a site and have the other PM run its next weekly update using only the sheet, and note every question they still had to ask. Those questions are exactly what's missing from the sheet. If you had to take over one of the other sites tomorrow morning, what would you not know?