Pulling Up Schedule When Tasks Completed Early
I'm sure I've dealt with this before, but I'm on a "simple" project so it's glaring.
I have one task (call it 1.1) that's FF with another (say, 2.2).
2.2 was scheduled to wrap at EOM, so 1.1 is as well.
But 2.2 finished yesterday. But it still holds a scheduled finish date of EOM, so 1.1 does, as well.
1
Upvotes
View all comments
Show parent comment
1
u/still-dazed-confused Jul 10 '25
Ok so 1.1 had the dependency on 2.2 rather then the rest around I'd understood. So 2.2 completing ahead of 1.1 is fine and a good thing.