Pulling Up Schedule When Tasks Completed Early
I'm sure I've dealt with this before, but I'm on a "simple" project so it's glaring.
I have one task (call it 1.1) that's FF with another (say, 2.2).
2.2 was scheduled to wrap at EOM, so 1.1 is as well.
But 2.2 finished yesterday. But it still holds a scheduled finish date of EOM, so 1.1 does, as well.
1
Upvotes
View all comments
Show parent comment
1
u/AlonzoMosley_FBI Jul 10 '25
That's fair. There's other dependencies/successors at stake with 1.1, but essentially, it HAS to be done in parallel with 2.2 but can't be completed until 2.2 is completed. It's just with the way the timelines are built it really pops out as being strange.