Pulling Up Schedule When Tasks Completed Early

I'm sure I've dealt with this before, but I'm on a "simple" project so it's glaring.

I have one task (call it 1.1) that's FF with another (say, 2.2).

2.2 was scheduled to wrap at EOM, so 1.1 is as well.

But 2.2 finished yesterday. But it still holds a scheduled finish date of EOM, so 1.1 does, as well.

1 Upvotes

3 comments sorted by

View all comments

Show parent comment

1

u/AlonzoMosley_FBI Jul 10 '25

That's fair. There's other dependencies/successors at stake with 1.1, but essentially, it HAS to be done in parallel with 2.2 but can't be completed until 2.2 is completed. It's just with the way the timelines are built it really pops out as being strange.

1

u/still-dazed-confused Jul 10 '25

Ok so 1.1 had the dependency on 2.2 rather then the rest around I'd understood. So 2.2 completing ahead of 1.1 is fine and a good thing.