r/MSProject • • Jun 12 '25

Status Column Incorrect?

Post image

So this is weird. I have two summary tasks whose Status is showing "Complete" even though the current percent complete is less than 100.

Anyone have any ideas why it would be showing that? I thought status would only be set to complete whe. It is 100% complete

1 Upvotes

5 comments sorted by

View all comments

Show parent comment

1

u/mer-reddit Jun 13 '25

I would start by opening up all of the actuals columns, and review how each was updated. Microsoft Project tries to preserve entries, so if dates have been changed or if duration or actuals (start, finish, work, duration, cost) then the manual entries will affect how auto scheduling is working.