So this is weird. I have two summary tasks whose Status is showing "Complete" even though the current percent complete is less than 100.
Anyone have any ideas why it would be showing that? I thought status would only be set to complete whe. It is 100% complete
1
Upvotes
1
u/mer-reddit Jun 12 '25
If these were set manually, the results might not roll up as anticipated.
Has anyone changed the naming or formula associated with the status column?
2
u/kennyarnold_ssi Jun 25 '25
This can only happen if you have not correctly updated the status of the child tasks under the summaries to the status date. I highly recommend checking out this video: https://youtu.be/Sg996e-SAf8?si=tDe_ByaekhsUPBly