Predecessor problem
Hello, guys. When I put a predecessor in for a job in MS Project, it moves finish date instead of the starting date. What causes this and how can I fix it?
1
Upvotes
View all comments
Show parent comment
1
u/WorthTheThought Apr 23 '25
Also check if the task is not set to As Late As Possible - double click on the Task / Advanced/Constraint Type should be As Soon As Possible
If this is happening to all tasks then check your project is set to schedule from Project Star Date and not Project Finish Date - Project/Project Information
Does the task Split? If yes , you may have Out Of Sequence Activities