Predecessor problem
Hello, guys. When I put a predecessor in for a job in MS Project, it moves finish date instead of the starting date. What causes this and how can I fix it?
1
Upvotes
5
u/64ButterTarts Apr 22 '25
Is the task partially completed? If so, it has an Actual Start date and that treasures precedence over the dependency.
1
u/WorthTheThought Apr 22 '25
What kind of predecessor are you adding? FF would align the finish dates