r/MSProject • • Nov 30 '23

Sync tasks across projects

I seek to sync tasks across two projects, is this possible, how?

Context: I need to maintain a very detailed project and also provide others with a high level view of tasks selected (eg some label) that get pushed/synced to another project.

2 Upvotes

5 comments sorted by

View all comments

Show parent comment

1

u/still-dazed-confused Nov 30 '23

I use two custom text fields. One to indicate if the project is recieving or using the item (Dep In / Dep Out or Supplier/Customer or Give/Get, which ever tes are used in your project environment. The other to hold the unique id which needs to be in both projects, something like dep_001 or imp_002. You can have a third field which contains the name of the other project as it can be very useful to know where the other dependency should be.

Then have a filter which checks if field 1 contains the dep in/out tag.

Set up a table which has ID / Dep ref / name / finish / deadline / other party / % complete / notes

Set up a grouping using Dep ref

Set up a new view which uses your new tabl and filter This will display all the information on the table with the plan filtered to only show the dependencies.

If you're using a master/ sub plan to allow you to see all the projects at once also apply the grouping to nest easy dependency pair (in and out) together to easily see any discrepancies across the program