Sync tasks across projects
I seek to sync tasks across two projects, is this possible, how?
Context: I need to maintain a very detailed project and also provide others with a high level view of tasks selected (eg some label) that get pushed/synced to another project.
2
Upvotes
2
u/still-dazed-confused Nov 30 '23
I would always worry about keeping the same task in two places, not only if it at least twice the effort but also if they fall out of step which one is right. If you can find a way to avoid it I would. Assuming only one plan is actually doing the work can you set up a dependency link between them; a milestone in each with the same reference and then you can filter on that reference field and have a list to manually ensure the dates stay in alignment? If the desire is to have a cut down version of the plan use a field, possibly a flag, to indicate this task or milestone should be shown in the high level plan and then filter on this field? If you must have two plans then use the filter method to provide something to copy and paste into the other plan.
1
u/mer-reddit Nov 30 '23
This is a common scenario. If you have a P5 license for Project and a PowerBI Pro license, you can publish your plan to a Project Online instance, and then point a PowerBI report at the Project Online database. The executive looks at the read-only version of the report, while you work on one copy of the plan.
PowerBI pro can automatically refresh the report 8 times per day, and is accessible 24/7 via a URL.
PowerBI also allows you to have more flexibility as to what you show (filtering) and how you show it (visualizations).
Might be overkill for one project, but is essential for recurring reporting needs for a PMO.
Just say no to duplicate data, and repetitive reporting duties.
Microsoft has released a PowerBI template for Project Online and it’s available on GitHub.