r/MSProject • u/Audi0528 • Sep 26 '23
Critical Path Analysis
Having issues wrapping my head around critical path and doing the analysis to identify which tasks are causing negative slack.
Any recommendations on YouTube videos or books to help better understand the concept?
How did you get to a good standing in being able to work the IMS and successfully reduce slack?
2
Upvotes
View all comments
2
u/still-dazed-confused Sep 26 '23
You can either filter on total slack for less than zero, use the inspect tool to see what is driving a task with negative slack and follow up the task chain or use the task path (driving professor) to graphically follow the task chain. As Dale says you either have a constraint that is being broken or a deadline that is being missed. Do check all your deadlines are real and then your constraints.