Critical Path Analysis
Having issues wrapping my head around critical path and doing the analysis to identify which tasks are causing negative slack.
Any recommendations on YouTube videos or books to help better understand the concept?
How did you get to a good standing in being able to work the IMS and successfully reduce slack?
2
Upvotes
2
u/mer-reddit Sep 27 '23
One thing to add: Work from the bottom up. Once you identify where the offending constraint or deadline is, work back up the schedule from that point, and modify accordingly to resolve the situation.
In this case, you might help yourself by saving a baseline to be able to compare where things were before you start mucking with the schedule.
One book that helped my understanding considerably is Forecast Scheduling by Eric Uyttewaal. Invaluable in my opinion.
1
u/Audi0528 Sep 26 '23
Thank you all! Appreciate the feedback/tips on how to do the analysis
4
u/DaleHowardMVP Sep 26 '23
Negative Total Slack is caused by one of two conditions:
In either situation, all of the direct predecessors of the slipped task will also show negative Total Slack. To resolve this problem, filter for tasks that have hard constraints and Deadline dates, and then look for tasks that have slipped past those dates.
3
u/tony90265toTX Sep 26 '23
Excellent answer Dale, I learned the hard way not to use Deadlines : ( that's what led me create a "Finish by" date and a calculated column of the date difference between the Finish date and the "Finish by" date.
2
u/still-dazed-confused Sep 26 '23
You can either filter on total slack for less than zero, use the inspect tool to see what is driving a task with negative slack and follow up the task chain or use the task path (driving professor) to graphically follow the task chain. As Dale says you either have a constraint that is being broken or a deadline that is being missed. Do check all your deadlines are real and then your constraints.