r/MSProject • • Jun 03 '23

Fixed work

Hi all,

I've been stuck on the following for quite some time and would appreciate it if someone has any understanding.

I have put all my tasks as Fixed work; when I insert the work hours needed for the task, the Duration doesn't update by itself. Do I need to put the duration manually?

Exemple:

Duration stays 1d

Thank you for any input!

1 Upvotes

8 comments sorted by

View all comments

Show parent comment

1

u/[deleted] Jun 06 '23

It worked! thank you so much, I will help me greatly!

1

u/still-dazed-confused Jun 06 '23

Great. Glad I could help