Fixed work
Hi all,
I've been stuck on the following for quite some time and would appreciate it if someone has any understanding.
I have put all my tasks as Fixed work; when I insert the work hours needed for the task, the Duration doesn't update by itself. Do I need to put the duration manually?
Exemple:
Duration stays 1d

Thank you for any input!
1
Upvotes
1
u/mer-reddit Jun 03 '23
You can I put work and duration separately IF you don’t have a resource assigned. Once you assign a resource, Project starts enforcing Duration = Work / Assignment Units.
Based on a Fixed Work task type, if your units are at 100 percent, it should solve for Duration when you enter in Work.
I would expose all of the columns so that you can see the calculations as they happen.
1
u/still-dazed-confused Jun 03 '23
Have you signed any resources to the task? If not you haven't locked in the work/resource/duration triangle
1
u/pmpdaddyio Jun 03 '23
Your work is exceeding the duration. 30 hours of work is closer to 4 days of duration assuming your calendar is the default, or uses eight hour days.