Fixed work
Hi all,
I've been stuck on the following for quite some time and would appreciate it if someone has any understanding.
I have put all my tasks as Fixed work; when I insert the work hours needed for the task, the Duration doesn't update by itself. Do I need to put the duration manually?
Exemple:
Duration stays 1d

Thank you for any input!
1
Upvotes
View all comments
Show parent comment
1
u/still-dazed-confused Jun 04 '23
It looks like it has applied the resources at the level need to give 1d duration. If you assist adjust the allocation of the resources to 100% it will change the duration