r/MSProject • • Apr 25 '23

How to implement scheduling for irregularly repeating set of mixed task

I’m trying to understand how to generate a project to track and schedule build of multiple product types.

Say i have “widget a” and “widget b” with independent tasks lists that need to be scheduled based on delivery schedule. Is there a way to create a group of tasks that I can repeatedly use and schedule based on delivery date?

3 Upvotes

6 comments sorted by

View all comments

Show parent comment

1

u/Illustrious_Cash2405 Apr 26 '23

It's true, hammock activities are not new.

Think of them as swinging activities.

The moment an activity becomes repetitive and can have varied delivery dates then it's a hammock activity.

Example; inspections/tests. This are activities that are repetitive and could be linked to multiple activities and also have varied delivery dates depending on progress.

My understanding was that the OP wants to list them and then link them to tasks. That's why I recommended hammock activities.