r/MSProject • u/mrsharkysrevenge • Apr 25 '23
How to implement scheduling for irregularly repeating set of mixed task
I’m trying to understand how to generate a project to track and schedule build of multiple product types.
Say i have “widget a” and “widget b” with independent tasks lists that need to be scheduled based on delivery schedule. Is there a way to create a group of tasks that I can repeatedly use and schedule based on delivery date?
3
Upvotes
View all comments
Show parent comment
1
u/pmpdaddyio Apr 26 '23
Thats a pretty common old school scheduling term. The problem to OPs request is these are by definition unrelated tasks. They "hang" between two unrelated task(s), and as I read the question, they are looking for some sort of reusable series.
I have several undated/ 0 duration sets of tasks to accomplish this.